Banas Road Construction|

 Road Works

  • Stripped asphalt off the entire length of the road. Intersections were left untouched and will be done at a later date.
  • Shaped and compacted subgrade.
  • Placed geotextile and subbase course material.

Culvert 

  • Installed the approach culverts on the east side of Banas Drive.
  • The culverts across Dawn Way have not yet been installed to maintain access for residents until access at the north end of Banas Drive is restored.