Banas Road Construction|

The current development schedule is as follows and is weather dependant:

  • August 17-21:
    • Complete ditching on Banas Dr and culvert installation (Banas Dr)
    • Final granular (gravel) placement (Banas/Carol)
    • Complete on-site grading of soil to a rough grade
  • August 24-28:
    • Final asphalt preparation on all roads and pathways with asphalt paving to follow
    • Asphalt paving of Carol Way first followed by Boulder Cres, with contractor to work their way out, and completion likely on the 26th
    • Banas Dr would be the end of the paving, starting likely on the 27th, finishing on the 28th.